NATIONAL MUNITIONS
COMPANY
Eldred
|
|
The largest McKean County war production
facility was the Eldred National Munitions Company. It was incorporated
in January 1941, and located along the Artline Road in Eldred Township,
just before the New York State line. The stock of the corporation
was owned by the Canadian American Company, Cleveland, OH. The original
fuse and shell loading plant, Plant No. 1, construction was started
in February 1941, and completed in August 1941. Many additions were
made to the original complex and the completion of Plant No. 4,
for the loading of incendiary bombs, was finished soon thereafter.
The property the company occupied totaled nearly 2,000 acres. The
first tract comprised of 235 acres and then an additional 1,500
acres near and across the state line was acquired. The area was
entirely surrounded by ranges of hills and two valleys known as
the Big Loop and the Little Loop Hollows. The isolation and topography
of the land made it especially adapted for a proving range for mortar
shells. The Eldred National Munitions Company was designed as a
loading plant rather than a manufacturing plant for mortar shells,
incendiary grenades, thermite aerial bombs and bomb fuses. Almost
all the production materials were received and completed assemblies
shipped by rail on the Pittsburgh, Shawmut & Northern Railroad.
The basic materials of operation—bomb shell bodies, fuse bodies,
exploder bags and ammunition were received ready for loading, processing
and final assembly. |
The 3-Inch Trench Mortar Bombs were
received complete with tail fins and loaded with 80-20 Amatol,
made up of 80% Ammonium Nitrate and 20% TNT. Amatol was a highly
explosive material, but extremely cheaper and easier to manufacture.
Amatol allowed the short supplies of TNT to be expanded considerably,
without reduction in the destructive power of the shells. This
was a highly attractive feature during war production when there
was such high demand for explosives. The bombs were received and
unpacked in the Shell Receiving building, cleaned and degreased
in the Cleaning building and transported by conveyor to the Shell
Loading building. Ammonium nitrate and TNT were brought down to
the Screening building, screened to remove any foreign substances
and transported to the Amatol Mixing building. On the third floor
of the building, the ammonium nitrate was heated in heating mixers
and the TNT was melted separately.
These two contents were mixed with the
proper proportion in Amatol mixers on the second floor, and dumped
through chutes to the first floor and loaded into steam-jacketed
Amatol buggies ready to be loaded into the shells. The shells
were loaded in two increments and pressed to the proper density
in hydraulic presses, the final press forming a cavity to receive
the paper cup fuse container. The container cup was sealed in
with molten TNT. From the Loading building the fuse was transported
by chain conveyor to the Assembly building. Here the bombs were
stenciled and striped with the proper identification markings.
A booster pellet or adapter was inserted in the container cup
and the fuse was screwed into place. A propelling cartridge was
inserted in the tail and six augmenting charges were inserted
between the fins. The tail cover was tied on, the fused bombs
placed in bomb carriers containing three bombs and two of these
carriers packed in an ammunition shipping case, stenciled and
ready for shipment. Bomb movement through these buildings was
by roller and belt conveyors.
The bomb line was tooled and equipped
to load 25,000 bombs per day. Pellet production of various sizes
were produced by the use of pellet presses. They included the
booster or adapter pellets for the bomb and the proper size of
pellets for the #119 and #152 fuses. Pellets of any size were
produced with these presses with the use of proper sized dies
and punches. These pellet presser were operated to turn out 20
pellets per minute. The Exploder Bag building was designed and
equipped for the loading of Exploder ‘B’ bags. The bags were loaded
by the use of a volumetric measuring device and settled to the
proper density by the use of a vibrating table designed and built
at the plant. Each of the dispensing machines had a capacity of
5,000 to 6,000 bags per shift. The #119 Fuse bodies were received
completely assembled and ready for loading. They were received
and unpacked in the Fuse Receiving building and started down the
loading line in Building 28. The fuses were first broken down
or disassembled, the component parts of each fuse being kept together
in one fuse block.
The fuse shutter was cleaned and scraped
ready for stemming. The shutters were stemmed with crystalline
dense tetryl, shellacked and covered with paper discs. Two detonators,
5-grain and 3-grain, were inserted in the holders and staked,
the firing channels stemmed and booster pellet inserted in the
magazine. Shutter springs were tested on a spinning device to
make sure that the shutter will arm between 1,300 and 1,700 revolutions.
The base cap on the magazine is crimped in place. After being
loaded the fuses are marked for identification, striped, proper
labels attached, packed in containers and placed in fuse shipping
boxes. The fuse line operated with a capacity of 5,000 to 6,000
per shift. The total capacity of the #119 Fuse lines could be
increased to 15,000 to 20,000 per day when the prompt receipt
of materials were available. The #152 Fuse assembly building was
equipped to turn out 25,000 fuses per day. The line equipment
and loading devices were similar to those of the #119 fuse production.
The operational steps for loading the #152 fuse were fewer. Only
one detonator, the 5-grain, is used in the fuse. The #152 fuses
were loaded for assembly for the 3 Inch Trench Mortar Bomb.
The employee capacity of the Eldred
National Munitions Company, exclusive of officers and salaried
executives and superintendents, was approximately 700 per eight
hour shift, or 2,100 per day on the basis of three shifts. Not
all divisions were fully tripled by three shifts and if necessary,
additional production lines could have been installed in most
divisions, increasing the employment and production capacity.
The employment was distributed as follows:
|
|
Bomb Line
Pellet Production
Exploder ‘B’ Bag Loading
#119 Fuse - 5 Lines
#152 Fuse - 8 Lines
Packing, Shipping, etc.
Guards, Maintenance, etc.
Subtotal:
TOTAL: 700
|
MEN:
100
7
3
7
4
35
95
251
|
WOMEN:
40
35
12
237
125
449
|
|
Based on the employment schedule and
production setup, the following production could be maintained as
long as adequate and prompt supply of component parts and loading
materials arrived as ordered. Early on during production, capacity
was not met because of the failure of other government contractors
to supply essential materials, particularly detonators: |
Bomb Line (1 line throughout)
Pellet Production
Exploder ‘B’ Bag Loading
#119 Fuse - 5 Lines
#152 Fuse - 8 Lines
|
PER SHIFT:
10,000
25,000
7,500
7,500
12,000
|
PER
DAY:
30,000
75,000
22,500
22,500
36,000
|
In 1941, the following contracts were
received by the Eldred National Munitions Company:
British Contract:
1) 1,500,000 Three (3) Inch Trench Mortar Shells loaded with
80-20 Amatol
2) 1,500,000 Fuses Percussion #152 Mark I/L
3) 1,000,000 Fuses Percussion #119 Mark IV/L
United States Contract:
1) 1,500,000 Clip Strikers, Crimping on Cartridges, Propelling
for 3 Inch Trench Mortar Bombs, Packing and Shipping.
2) 1,500,000 Three (3) Inch Trench Mortar Shells loaded with
80-20 Amatol
3) 1,625,000 Fuses Percussion #152 Mark I/L 4) 3,466,666 Incendiary
Bombs
The munitions company maintained a
well equipped first aid hospital. The building contained wards
for men and women, receiving room, examination room, nurse’s
room, diet kitchen and all the necessary medical equipment and
supplies. Trained nurses were on duty during all shifts and
a physician was in attendance each forenoon, and on call at
all times. A steam laundry building was available to take all
the uniforms and overalls of all persons working with Tetryl
or TNT must be changed and laundered everyday. The men’s changing
house contained shower baths, lockers, wash fountains and a
lounge for the men. All men working with Tetryl or TNT were
required to take a bath and change their clothes everyday as
a protection against poisoning. As with the men’s change house,
there was also a women’s change building No. 32, located across
the plant road from the fuse loading buildings. It contained
a locker room, rest rooms, wash room and shower baths. Time
clocks for the women were located at the entrance. As with the
men, any women working with Tetryl, stemming, etc., must take
baths and change work clothes daily. Electric power was supplied
to the plant by the Bradford Electric Company and there were
over 10,000 feet of power lines constructed between the various
buildings. The power house used coal feeding boilers to produce
steam for the facilities. Over 9,000 feet of steam pipes, insulated
and covered with water proofing, supplied all the buildings.
The munitions company also operated its own narrow gage railroad
for transportation throughout the plant complex with over two
miles of track. Three Plymouth gasoline locomotives, models
RL & RLH, operated with anti-fire safety features of the exhaust
through water. There were fifteen specially designed tram cars
for hauling the materials.
CORPORATE OFFICERS:
J.
A. Wigmore
Colonel J. Q. MacDonald
J. C. Bashford
Myron Ulrich
G. G. Peckham
Ford H. MacGregor
Harris M. Susselman
George M. Roudebush
John E. Welsby
PLANT MANAGEMENT:
J.
C. Bashford
Ford H. MacGregor
C. L. Carlson
John E. Welsby
Frank Faye
H. H. Hopkins
Norbart Forness
Charles Locke
Caleb Jones
Donald Guerin
Frank Breck
|
President
1st Vice President
2nd Vice President
Secretary
Treasurer
Asst Secretary and Treasurer
Asst Secretary
General Council
Technical Advisor
General Manager
Asst Secretary and Treasurer
Auditor and Office Manager
Technical Advisor
Pay Master
Asst to General Manager
Asst to Superintendents
Maintenance Superintendent
Shell Loading Superintendent
Chief of Guards
Fuse Loading Foreman
|
|
|